Solar permitting in Duval County has fallen sharply over the past year. This piece uses recorded permits in Poach.rr's dataset for the market, collected from public permit portals. It is not a count of every permit issued in the county.
October 2026 at a glance
Our dataset shows 29 solar permits for October 2026. October 2025 had 55, so the month is down 47.3% year over year. September 2026 was nearly identical at 28, so October is not a one-month dip. It is the second month in a row at a much lower level than the summer.
The latest month can be incomplete, because some portals publish filings late. Treat the October count as provisional and expect it to be revised as late filings arrive.
Trailing 12 months vs the prior 12
| Period | Solar permits |
|---|---|
| Trailing 12 months (through October 2026) | 392 |
| Prior 12 months | 1,009 |
That is a 61.1% decline. The comparison covers 12 full months on each side, so it does not depend on the unfinished October figure.
How the 24 months unfolded
The monthly series shows the shape of the decline:
- Late 2024 to mid-2025: Counts ran from 112 in December 2024 down to 82 in July 2025. Every month in between was between 83 and 106.
- Late 2025: The count dropped to 55 in August 2025 and 42 in September 2025. It then ran 55, 49 and 33 through December 2025.
- First half of 2026: Monthly counts stayed between 18 and 22. April 2026 was the low at 18.
- Summer 2026: The count jumped to 70 in July and 61 in August.
- Autumn 2026: It fell back to 28 in September and 29 in October.
Our data does not show why the July and August 2026 counts jumped, and we will not guess. What it does show is that the first half of 2026 ran far below the same months of 2025. For example, March 2025 had 98 permits and March 2026 had 19.
Which installers pulled the most permits
Over the window in our dataset, these installers appear most often on Duval solar permits:
| Installer | Permits |
|---|---|
| Top Tier Solar Solutions | 49 |
| Nick's Solar & Air Systems | 22 |
| A1A Solar Contracting | 17 |
| Jimmy's Electric | 15 |
A fifth installer, not named in this table, recorded 21 permits, putting it between the second and fourth names above. Top Tier Solar Solutions stands well apart from the rest at 49. Below it, the field is tightly bunched between 15 and 22 permits. With volume this low, no installer has a dominant base of recent work. A single good month can move an installer up the list.
System sizes are not available for this market in our data, so we cannot say whether the typical installation has grown or shrunk.
Roofing context in the same county
Roofing is much larger than solar here. Our dataset holds 10,865 roofing permits in the trailing 12 months, an average of 905 a month. The peak was April 2026 at 1,487. Nearly all of them, 10,864, sit in Jacksonville. Replacements make up 83.2% of roofing permits and repairs 1.3%.
October 2026 shows zero roofing permits in our dataset. Read that as an incomplete month, not a collapse. We have no prior-year roofing comparison for this market, so we are not drawing a roofing trend from the month.
Roof age: where the older roofs are
We track 16,961 homes with roof-age information in the county. The breakdown:
- Under three years: 10,805 homes
- Three to nine years: 2,795 homes
- 10 to 14 years: 1,546 homes
- 15 to 19 years: 875 homes
- 20 years or more: 940 homes
Homes with roofs 15 years or older are 10.7% of those tracked. The market is dominated by recently roofed homes, which is relevant to solar: a young roof is usually a clean candidate for panels, while an older one often needs a decision before racking goes on.
What this means for roofers
- Solar is a small lead source right now. With 392 solar permits in the trailing 12 months, versus 10,865 roofing permits, roof-before-solar jobs will not be a large share of your pipeline in Duval.
- Target the older roofs. The 875 homes at 15 to 19 years and 940 at 20 or more are the ones where a roof-first conversation makes sense if an owner is weighing solar. Partnering with one of the active installers is a practical route.
- Expect fewer re-roof-for-solar calls. If you relied on installers sending roof work ahead of an install, the drop from 1,009 to 392 permits suggests less of it is coming.
What this means for solar installers
- The market has contracted, and the field is thin. Five names account for most of the repeat activity, and only one is well clear of the pack.
- Mind the roof. Most tracked homes have roofs under three years old, so many are ready for panels now. Older roofs may stall a sale unless you line up a roofing partner.
- Watch the summer pattern. July and August 2026 stood out at 70 and 61, then September and October fell back. Whether that repeats is something to check against the next few months of data.
Caveats
Coverage depends on which jurisdictions publish permits, so the counts are recorded permits, not a full census. The October figures, especially roofing, may rise as late filings come in.
Frequently asked questions
How many solar permits were pulled in Duval County in October 2026?
Our dataset shows 29 solar permits for October 2026, versus 55 in October 2025, a 47.3% decline. The latest month can be incomplete because some portals publish late.
Are Duval County solar permits up or down over the past year?
Down. The trailing 12 months show 392 recorded solar permits versus 1,009 in the prior 12 months, a 61.1% decline.
Which installers pulled the most solar permits in Duval County?
Top Tier Solar Solutions leads with 49 permits in our dataset. Nick's Solar & Air Systems follows with 22, then A1A Solar Contracting with 17 and Jimmy's Electric with 15, with one more installer at 21.
What is the typical solar system size in Duval County?
We cannot say. System-size data is not available for this market in our dataset.
How old are the roofs in Duval County?
Of 16,961 homes tracked, 10,805 have roofs under three years old. Homes with roofs 15 years or older are 10.7% of the total, including 940 at 20 years or more.
Methodology
Counts are residential roofing and solar building permits in Poach.rr's dataset for Duval County, FL, collected from public county and city permit portals. Coverage depends on which jurisdictions publish permits, so read the numbers as a consistent sample, not a census of every permit filed. Months where a source feed was incomplete are excluded from comparisons, and the latest month can rise as portals publish late filings. Data runs through October 2026; page generated November 21, 2026.